Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

May 10, 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 5/11

1 BP: 

  • No work planned at this time

2 BP:

  • National Grid gas connection service at SW corner, along with street paving
  • Mechanical work at penthouse and shafts
  • Curtain wall and terracotta install
  • Interior gypsum wall board hanging
  • Roofing

Monday, 5/13 –Friday, 5/17:

Site Operations:

  • Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week
  • Subcontractors to move trailers off site

Earthwork

1 BP:

  • Soils and curb work garage north and east, and 1 BP south along Washington

Façade/Roof:

1BP:

  • Complete metal panels at north vestibule
  • Complete snap covers and metal clad at north parapet

2BP:

  • Level 4 parapet
  • Rooftop rail installation
  • Curtain wall installation to be completed
  • Terracotta at south and west façade to continue
  • Level 1 framing at awnings to be completed
  • Level 1 metal panels to be installed
  • Boston Children’s signage at Level 9 west ready for metal supports and terracotta
  • Granite base install

Building Interior / Utilities:

1BP:

  • Final paint
  • Final MEP controls and building controls to be connected and tested
  • Carpeting at connectors floors 2 and 6

2BP:

  • Moisture mitigation
  • Interior gypsum wall board partitions buildout on east side
  • Sheathing and sheet blocking at generator curb
  • MEP installations on-going at all floors
  • Elevator equipment installation
  • Firestopping in multiple areas

Future Activities:

Site Operations:

  • Brookline Avenue street work for 1BP addition fire pump connection
  • Remaining overhead sidewalk protection removal weekend of 5/18
  • Temp loading dock and material hoist to be disassembled

Earthwork

1 BP:

  • Landscaping and hardscaping
  • Pavers and concrete placements

2BP:

  • Soil grading at loading dock
  • Catenary light poles
  • Final soils and hardscaping

Façade/Roof:

1BP:

  • North canopy glass to be installed

2BP:

  • Louver installation
  • SW corner level 1 glass to be installed
  • Terracotta installation to be completed
  • Construct loading dock entrance and door
  • Exterior doors/entrances complete
  • Exterior signage

Building Interior / Utilities:

1BP:

  • Addition lobby millwork and finishes complete
  • Final firestopping/T-rating installations
  • Final cleaning
  • Interior signage

2BP:

  • Final MEP controls and building controls to be connected and tested
  • Drywall finish and final paint
  • Locker room, bike room and bathroom buildout
  • Specialties, millwork and finishes

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.